WP2 | Q2 - Q3 2005 | procure EMCCD's |
WP2 | Q3 2005 - Q1 2006 | characterise EMCCD's in laboratory |
WP2 | Q2 - Q3 2006 | characterise EMCCD's on telescope |
WP5 | Q2 - Q3 2005 | test high-voltage clock board with new EMCCD's |
WP5 | Q3 - Q4 2005 | design, manufacture and test final version of high-voltage clock board |
WP6 | Q3 2005 - Q1 2006 | design and write full suite of DSP applications |
WP6 | Q3 2005 - Q1 2006 | write spectroscopic version of ULTRACAM pipeline data reduction system |
WP7 | Q2 - Q3 2005 | modify camera head to accommodate new EMCCD's |