Ultracam Progress Meeting - 28 February 2001
Attendees: Derek Ives, Chris Tierney, Tully Peacock, Gayle Reynolds, David Atkinson
Absences: Vikram Dhillon, Andy Vick
Notes of Meeting:
· Optical
Tully reported that he has revised the optics and removed the glass for the re-design without any problems.
With regards to the Collimator design, he will take 2 days overtime (weekend) to do this. Derek to clear this with Gary Rae.
· Electronics/Mechanical
Brian Wilson is currently wiring the cables.
David will soon be carrying out vacuum tests for the camera head. There has been a problem so far in keeping the vacuum but this could have been caused by a faulty seal. This has now been remachined and he will do a clean assembly test either today or tomorrow.
· Software
Chris didn't have any new issues to raise.
Derek reported that he had checked the budget and there is currently £22k left to spend on things like a new PC, tech controllers, racks, cables etc, but even this will leave enough aside for approx 1.2 staff years of effort.
ACTION: Chris to report back to Derek in one month with an overall figure for software effort.
· AOB
Andy Vick will be taking over the meetings in 2 weeks time.
The CDR will be held on 2nd May 01 and delivery should be by 1 Nov 01.
Detail of Action |
Owner |
Date Raised |
Target Closure Date |
Forecast Closure Date |
Status/Comments |
First Draft (use cases and initial object modules) of software design |
Chris Tierney/ Andy Vick |
01-Oct-00 |
25-Oct-00 |
01-Feb-00 |
|
Set up access to shared work area for UML models |
Andy Vick/ Chris Tierney |
01-Oct-00 |
01-Dec-00 |
01-Jan-00 |
|
Arrange for Vicki to have access to Ultracam directories/files on NT system |
Derek Ives |
01-Nov-00 |
02-Nov-00 |
29-Nov-00 |
Folder now set up on NT 'Projects' Directory. Team in process of moving relevant files to this folder. [To close] |
Forecasts to be completed on outturns and also EAS to be submitted |
Derek Ives |
15-Nov-00 |
17-Nov-00 |
04-Dec-00 |
Outturns Forecast Complete.
Derek to confirm EAS is as required.
|
Attendance required at next PMM to emphasise lack of software support available. |
Derek Ives |
15-Nov-00 |
6-Feb-01 |
6-Feb-01 |
Will be attending next meeting. |
Chris to report back to Derek in one month with an overall figure for software effort. |
Chris Tierney |
28-Feb-01 |
30-Apr-01 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|