Ultracam Progress Meeting - 14 February 2001


Attendees: Derek Ives, Chris Tierney, Tully Peacock, Vicki Ramsay, David Atkinson


Absences: Vikram Dhillon, Andy Vick


Notes of Meeting:


· Optical

Three quotations have been received for the optics. One is coming across better (Specak) due to the fact that it is affordable (£25K) and they will take responsibility not only for manufacturing but also mounting. We have good experience with this company.


Tully has changed design to use new glass but test results with this new spec are fine. Tully is awaiting a reply from Vik before he finalises the drawings/design ready for manufacture. These changed will mean that Sheffield will have to change mechanical fitting drawings.


· Electronics/Mechanical

David has been doing cabling work and test boxes. He will be beginning to get familiar with the DSP & SDSU works.

Other progress items:


Red optmised CCD has come in. This was to be manufactured to a specified 'typical value' for dark current, but the delivered CCD has near maximum typical values for dark current. If it does not meet requirements the supplier have agreed to take it back and supply another CCD. Having difficulty producing other two devices (three month delay).


· Software

Software are now getting underway and Andy & Chris have managed four days worth of design work.

Main concerns at the moment are about the internal of camera system and GUI. They are working on command line input with GUI and trying to get web interface going with this, and need at some point to get Derek and David re interface and DSP code.

High level software is being designed in and they are trying to design software that can be moved to another camera if needed (XML code).


Derek queried if time stamping was fitting into model and Chris does not see a problem with this - the dual processor is helping with this. Will use an optical RS232 fibre link from GPS receiver to the PC. This still allows lightning protection instead of using the radio broadcast system.


Cannot provide estimate yet as to how much time the software effort will take, but will provide this before the Review. Have a lot of design but need to tightening it up.


· AOB


Director's Review on 22nd and David Atkinson is completing the PowerPoint presentation for this.

Design Review is scheduled to take place on 28th March, but a time is still to be confirmed.

ACTIONS



Detail of Action

Owner

Date Raised

Target Closure Date

Forecast Closure Date

Status/Comments

First Draft (use cases and initial object modules) of software design

Chris Tierney/ Andy Vick

01-Oct-00

25-Oct-00

01-Feb-00


Set up access to shared work area for UML models

Andy Vick/ Chris Tierney

01-Oct-00

01-Dec-00

01-Jan-00


Arrange for Vicki to have access to Ultracam directories/files on NT system

Derek Ives

01-Nov-00

02-Nov-00

29-Nov-00

Folder now set up on NT 'Projects' Directory. Team in process of moving relevant files to this folder. [To close]

Forecasts to be completed on outturns and also EAS to be submitted

Derek Ives

15-Nov-00

17-Nov-00

04-Dec-00

Outturns Forecast Complete.


Derek to confirm EAS is as required.


Attendance required at next PMM to emphasise lack of software support available.

Derek Ives

15-Nov-00

6-Feb-01

6-Feb-01

Will be attending next meeting.