Ultracam Progress Meeting - 21 March 2001


Attendees: Andy Vick, Tully Peacock, David Atkinson, Vicki Ramsay


Absences: Derek Ives, Chris Tierney, Vikram Dhillon


Notes of Meeting:


· Optical


Contract for manufacture has been put out to tender.

Tully has also started Aristorchos drawing work - this has to be done under HIE support scheme and is not officially part of project, but is integral part.

Tully is away the week before and week after Easter.


· Mechanical


Still nothing to report on mechanical.

Mechanical team want to come a see Tully and this needs to be scheduled - will take maybe a full day.

[Suggestion from Vik is that this should be the 11th April (Wednesday).]


· Electronics


Currently using Engineering grade CCD - won't use science grade for a couple of months. One science array is not to spec and is to be replaced.

Have pictures at room temp using CCD and this is now under vacuum and cooled.

David still has a learning curve with DSP code etc and is steadily working his way through this work

Chris had meeting with Derek & David for software plans - David believes there was nothing unworkable in this.


· Software


Ultracam PCI board is in lab, in WFCAM PC. Derek will be using this for the moment until Voodoo is up and running. Not sure what stage he is at yet.

Chris may have some time is a week or two to assist with reading out array of PCI bus

Andy will not have time to work on system until 9th of April (currently tied up with NAOMI).


· AOB

Andy calling Vikram to discuss progress after meeting.

CDR is now postponed. Provisional date of Wednesday 9th May has been set.

Documentation for this should be ready by 27th April as these should be with Sheffield by 2nd May (need description of system planning to be built [assessment design]).

Open Day to be held on 13th & 14th of April, Vikram has a poster we can use if required.


ACTIONS



Detail of Action

Owner

Date Raised

Target Closure Date

Forecast Closure Date

Status/Comments

First Draft (use cases and initial object modules) of software design

Chris Tierney/ Andy Vick

01-Oct-00

25-Oct-00

01-Feb-00


Set up access to shared work area for UML models

Andy Vick/ Chris Tierney

01-Oct-00

01-Dec-00

01-Jan-00


Arrange for Vicki to have access to Ultracam directories/files on NT system

Derek Ives

01-Nov-00

02-Nov-00

29-Nov-00

Folder now set up on NT 'Projects' Directory. Team in process of moving relevant files to this folder. [To close]

Forecasts to be completed on outturns and also EAS to be submitted

Derek Ives

15-Nov-00

17-Nov-00

04-Dec-00

Outturns Forecast Complete.


Derek to confirm EAS is as required.


Attendance required at next PMM to emphasise lack of software support available.

Derek Ives

15-Nov-00

6-Feb-01

6-Feb-01

Will be attending next meeting.

Chris to report back to Derek in one month with an overall figure for software effort.

Chris Tierney

28-Feb-01

30-Apr-01