timescales



ULTRACAM will see first light on the GHRIL focus of the 4.2-m William Herschel Telescope (WHT) on La Palma during early autumn 2001. This web-page shows the Gantt chart for the project, which details the status of the individual ULTRACAM work packages.

There are two major milestones in the project, denoted by the letters CDR and ATR in the Gantt chart. These represent review meetings attended by all of the project members.

CDR Critical design review. Detailed design of every part of the instrument presented. Confirm project is on course for successful completion and identify any elements of the detailed design which need further work. Start construction of the component parts and coding of the software.
ATR Acceptance Test Review. Demonstrate that ULTRACAM is complete and that its performance meets the requirements.

Gantt chart:   Project overview.

task

% done

08/99

09/99

10/99

11/99

12/99

01/00

02/00

03/00

04/00

05/00

06/00

07/00

08/00

09/00

10/00

11/00

12/00

01/01

02/01

03/01

04/01

05/01

06/01

07/01

08/01

09/01

10/01

                                                         
CONTRACT (UKATC/SHEFFIELD/SOUTHAMPTON)                                     CDR             ATR    
select contractor 100                                   CDR             ATR    
define requirements 100                                   CDR             ATR    
draft and sign contract 100                                   CDR             ATR    
                                                         
OPTICAL SYSTEM (UKATC/SHEFFIELD)                                                   ATR    
design 100                                   CDR             ATR    
order optics 50                                   CDR             ATR    
design mountings 10                                   CDR             ATR    
manufacture mountings 0                                   CDR             ATR    
acceptance testing 0                                   CDR             ATR    
                                                         
CCD/DAS (UKATC)                                                   ATR    
order SDSU controller and CCDs 100                                   CDR             ATR    
preliminary camera head and software design 100                                   CDR             ATR    
detailed camera head design 100                                   CDR             ATR    
detailed SDSU and DAS software design 0                                   CDR             ATR    
mechanical/electronics manufacture 0                                   CDR             ATR    
SDSU and DAS coding 0                                   CDR             ATR    
camera system integration 0                                   CDR             ATR    
acceptance testing 0                                   CDR             ATR    
                                                         
PIPELINE DATA REDUCTION SOFTWARE (SOUTHAMPTON) 0                                                 ATR    
design 25                                   CDR             ATR    
coding 0                                   CDR             ATR    
                                                         
OPTO-MECHANICAL CHASSIS (SHEFFIELD) 0                                                 ATR    
design 25                                   CDR             ATR    
manufacture 0                                   CDR             ATR    
                                                         
COMPLETION (SHEFFIELD/WHT) 0                                   CDR             ATR    
apply to ING/PATT for commissioning/observing time 0                                   CDR             ATR    
final integration 0                                   CDR             ATR    
packing and shipping 0                                   CDR             ATR    
engineering and astronomical commissioning at telescope 0                                   CDR             ATR